[ARCHIVED] Brentwood Bound Construction Update – July 14, 2022

Brentwood Bound Construction Update

On-site construction work details anticipated in the next two weeks on the Brentwood Bound projects:

Flood Mitigation Phase 1

  • Multi-use trail installation
  • Pond liner installation
  • Landscaping improvements 
  • Remaining sheet pile wall installation near Exchange Way (tentative start)

Flood Mitigation Phase 2

  • Completion of pipe-in tunnel beneath Manchester Road
  • Breckenridge Industrial Court bridge installation
  • Sanitary sewer junction chamber excavation, shoring and construction
  • Sanitary sewer piping installation

Deer Creek Greenway Connector Part A

  • Flatwork, curb/gutter and roadway installation
  • Site utilities rough-in
  • Completion of remaining storm sewers
  • Excavation and construction of the bioretention basin
  • Construction of large Dumpster enclosure near Brazeau Avenue
  • Permeable paver parking lot construction (tentative start)

Event Lawn/Comfort Station 

  • Completion of standing seam metal roof
  • Exterior concrete pavement and sidewalk installation
  • Exterior stonework
  • Installation of the Ameren transformer and primary power cables
  • Windows and wood siding installation

MoDOT Manchester Road Improvements

  • Sawcutting, removals, and linear grading
  • Form and pour sidewalks, curb ramps, curbs, gutters, and approaches 
  • Sanitary sewer installation and storm sewer improvements
  • Pedestrian underpass construction
  • Manchester Road closures, demo and intersection work at/near Hanley Road
  • Black Creek bridge construction

Site Cameras

See a live view of work on Brentwood Bound through the “Site Cameras” link at the top of the home page of www.BrentwoodBound.org.  

Learn more about Brentwood Bound at www.BrentwoodBound.org.