On-site construction work details anticipated in the next two weeks on the Brentwood Bound projects:
Flood Mitigation Phase 1
- Modular block retaining wall installation
- Multi-use trail installation
- Irrigation water line installation
- Pond liner installation
- Landscaping improvements
- Sewer pipe testing
- Remaining sheet pile wall installation near Exchange Way
Flood Mitigation Phase 2
- Breckenridge Industrial Court bridge construction
- Sanitary sewer junction chamber excavation, shoring and construction
- Sanitary sewer piping and structure(s) installation
- Sheet pile wall installation along Black Creek near Breckenridge Material Co.
Deer Creek Greenway Connector Part A
- Roadway installation
- Subgrade remediation beneath the multi-use trail
- Multi-use trail installation
- Construction of dumpster enclosures near Brazeau and Mary avenues
- Permeable paver parking lot construction
Event Lawn/Comfort Station
- Exterior stone are complete
- Painting of restroom ceilings and event space
- Insulation and wood siding installation
- Completion of MEP trim in all areas
- Construction of footings for Food Truck Plaza light poles
MoDOT Manchester Road Improvements
- Demo, grading and utility work
- Flatwork installation(s)
- Pedestrian underpass construction
- Manchester Road closures and intersection work at Hanley Road
- Black Creek Bridge construction
Site Cameras
See a live view of work on Brentwood Bound through the “Site Cameras” link at the top of the home page of www.BrentwoodBound.org.
Learn more about Brentwood Bound at www.BrentwoodBound.org.