On-site construction work details anticipated in the next two weeks on the Brentwood Bound projects:
Brentwood Bound Construction Update – August 18, 2022
On-site construction work details anticipated in the next two weeks on the Brentwood Bound projects:
Flood Mitigation Phase 1
- Multi-use trail installation
- Irrigation water line installation
- Pond liner installation
Flood Mitigation Phase 2
- Breckenridge Industrial Court bridge construction
- Sanitary sewer junction chamber excavation, shoring and construction
- Sanitary sewer piping and structure(s) installation
- Sheet pile wall installation along Black Creek near Breckenridge Material Co.
Deer Creek Greenway Connector Part A
- Roadway and remaining flatwork installation
- Multi-use trail installation
- Construction of dumpster enclosures near Brazeau and Mary avenues
- Permeable paver parking lot construction
Event Lawn/Comfort Station
- Painting of doors, frames and timber frame connections
- Installation of exterior wall insulation, wood siding and metal panels
- Completion of mechanical and electrical trim in all areas
- Grinding of concrete floors
- Masonry wall cleaning
- Final grading of event lawn and food truck plaza
MoDOT Manchester Road Improvements
- Demo, sawcutting and utility work
- Flatwork installation(s)
- Electrical rough-in (Helen to Porter)
- Pedestrian underpass construction
- Manchester Road closure(s) and intersection work at Hanley Road
- Black Creek bridge construction
Site Cameras
See a live view of work on Brentwood Bound through the “Site Cameras” link at the top of the home page of www.BrentwoodBound.org.
Learn more about Brentwood Bound at www.BrentwoodBound.org.
Site Cameras
See a live view of work on Brentwood Bound through the “Site Cameras” link at the top of the home page of www.BrentwoodBound.org.
Learn more about Brentwood Bound at www.BrentwoodBound.org.