On-site construction work details anticipated in the next two weeks on the Brentwood Bound projects:
On-site construction work details anticipated in the next two weeks on the Brentwood Bound projects:
Flood Mitigation Phase 1
- Multi-use trail installation (tentative)
- Irrigation water line installation (tentative)
- Landscaping improvements (tentative)
- Pond liner installation
- Installation of the revetment scour mat at Pond
Flood Mitigation Phase 2
- Breckenridge Industrial Court bridge construction
- Sanitary sewer junction chamber excavation, shoring and construction
- Sanitary sewer piping and structure(s) installation
Deer Creek Greenway Connector Part A
- Roadway and remaining flatwork installation
- Multi-use trail installation
- Utilities installation
- Demo, fill and improvements at 8702 Manchester parking lot
Event Lawn/Comfort Station
- Final painting in all areas
- Finishing up exterior wood siding
- Completion of mechanical and electrical trim in all areas
- Grinding and sealing of concrete floors
- Completion of food truck plaza concrete paving
MoDOT Manchester Road Improvements
- Demo, sawcutting, removals and utility work
- Flatwork installation(s)
- Demolition and construction for pedestrian underpass
- South traffic stage change for pedestrian underpass (north)
- Manchester Road closure(s) and intersection work at Hanley Road
- Black Creek bridge construction
Site Cameras
See a live view of work on Brentwood Bound through the “Site Cameras” link at the top of the home page of www.BrentwoodBound.org.
Learn more about Brentwood Bound at www.BrentwoodBound.org.