On-site construction work details anticipated in the next two weeks on the Brentwood Bound projects:
On-site construction work details anticipated in the next two weeks on the Brentwood Bound projects:
Flood Mitigation Phase 1
- Retaining wall installation
- Multi-use trail installation
- Irrigation water line installation
- Landscaping improvements
- Installation of coir and revetment scour matting at the Pond
- Earthwork near main office trailer
Flood Mitigation Phase 2
- Breckenridge Industrial Court bridge construction
- Sanitary sewer junction chamber excavation, shoring and construction
- Sanitary sewer piping and structure(s) installation
Deer Creek Greenway Connector Part A
- Remaining curb installation and asphalt paving
- Multi-use trail and amphitheater sidewalk installation
- Placement of landscape and retaining boulders at the Pond
- Site utilities installation
- Improvements at 8702 Manchester parking lot
- Dumpster enclosure construction and masonry
Event Lawn/Comfort Station
- Completion of building punchlist work
- Completion of food truck plaza concrete paving
- Installation of lawn irrigation systems
- Brentwood IT and PASS completion of data, security and access control work
MoDOT Manchester Road Improvements
- Demo, sawcutting, removals and utility work
- Flatwork installation(s)
- Pedestrian underpass construction (north)
- Manchester Road intersection electrical/flatwork at Hanley Road
Site Cameras
See a live view of work on Brentwood Bound through the “Site Cameras” link at the top of the home page of www.BrentwoodBound.org.
Learn more about Brentwood Bound at www.BrentwoodBound.org.