[ARCHIVED] Brentwood Bound Construction Update - October 13, 2022

BB Construction Update

On-site construction work details anticipated in the next two weeks on the Brentwood Bound projects:

Flood Mitigation Phase 1

  • Retaining wall installation
  • Multi-use trail installation 
  • Irrigation water line installation 
  • Landscaping improvements 
  • Installation of revetment scour matting at the pond

Flood Mitigation Phase 2

  • Breckenridge Industrial Court bridge construction
  • Sanitary sewer junction chamber construction
  • Sanitary sewer piping and structure(s) installation
  • Earthwork south of Deer Creek along Black Creek

Deer Creek Greenway Connector Part A

  • Multi-use trail and amphitheater flatwork installation
  • Amphitheater retaining seat wall installation
  • Site utilities installation
  • Landscaping improvements

Event Lawn/Comfort Station 

  • Completion of building punchlist work
  • Tree planting

Destination Playground

  • Temporary fencing installation
  • Site clearing and tree removal
  • Starting earthwork and site utilities

MoDOT Manchester Road Improvements

  • Demo, grading and utility work
  • Flatwork installation(s)
  • Electrical work
  • Pedestrian underpass construction (north)
  • Manchester Road intersection flatwork at Hanley Road

Site Cameras

See a live view of work on Brentwood Bound through the “Site Cameras” link at the top of the home page of www.BrentwoodBound.org.  

Learn more about Brentwood Bound at www.BrentwoodBound.org.

Facebook Twitter Email

Other News in Brentwood Bound

Brentwood Bound Brentwood Park

Coming in 2023: Brentwood Park

Posted on: January 4, 2023
Brentwood Bound Pedestrian Tunnel

Coming in 2023: Pedestrian Tunnel

Posted on: January 4, 2023
Playground Groundbreaking 11.3.22

Destination Playground Groundbreaking

Posted on: November 3, 2022