On-site construction work details anticipated in the next two weeks on the Brentwood Bound projects:
On-site construction work details anticipated in the next two weeks on the Brentwood Bound projects:
Flood Mitigation Phase 1
- Retaining wall installation
- Multi-use trail installation
- Irrigation water line installation
- Landscaping improvements
- Sewer pipe testing
Flood Mitigation Phase 2
- Breckenridge Industrial Court bridge construction
- Sanitary sewer junction chamber construction
- Sanitary sewer piping and structure(s) installation
- Earthwork south of Deer Creek along Black Creek
Deer Creek Greenway Connector Part A
- Multi-use trail and amphitheater flatwork installation
- Amphitheater retaining seat wall installation
- Boardwalk, boulder, and dry stream installation
- Site utilities installation
- Parking stop installation at 8702 Manchester Road parking lot
- Underground low-voltage conduit installation
- Landscaping improvements
Event Lawn/Comfort Station
- Completion of building punchlist work
- Final punchlist walkthrough
Destination Playground
- Temporary fencing installation
- Site clearing and tree removal
- Starting earthwork and site utilities
MoDOT Manchester Road Improvements
- Demo, grading and utility work
- Flatwork installation(s)
- Electrical work
- Pedestrian underpass construction (north)
Site Cameras
See a live view of work on Brentwood Bound through the “Site Cameras” link at the top of the home page of www.BrentwoodBound.org.
Learn more about Brentwood Bound at www.BrentwoodBound.org.