On-site construction work details anticipated in the next two weeks on the Brentwood Bound projects:
On-site construction work details anticipated in the next two weeks on the Brentwood Bound projects:
Flood Mitigation Phase 1
- Stream stabilization work
- Multi-use trail installation
- Irrigation water line installation
- Landscaping improvements
- Sewer pipe testing
- Diversion Structure flatwork
Flood Mitigation Phase 2
- Breckenridge Industrial Court bridge approach work
- Sanitary sewer junction chamber construction
- Sanitary sewer piping and structure(s) installation
- Earthwork south of Deer Creek along Black Creek
Deer Creek Greenway Connector Part A
- Multi-use trail installation
- Boardwalk, boulder wall, and dry stream installation
- Site utilities installation
- Light pole base and parking stop installation at 8702 Manchester
- Underground low-voltage conduit installation
- Landscaping improvements
Event Lawn/Comfort Station
- Completion of building punchlist work
Destination Playground
- Starting installation of the sewer piping from the intersection of Brazeau Avenue and Pendleton Avenue
- Starting earthwork activities
- Starting installation of the storm sewer piping onsite
MoDOT Manchester Road Improvements
- Demo, grading and utility work
- Flatwork and asphalt approach installation(s)
- Pedestrian underpass construction (north)
Site Cameras
See a live view of work on Brentwood Bound through the “Site Cameras” link at the top of the home page of www.BrentwoodBound.org.
Learn more about Brentwood Bound at www.BrentwoodBound.org.