[ARCHIVED] Brentwood Bound Construction Update - December 8, 2022

BB Construction Update

On-site construction work details anticipated in the next two weeks on the Brentwood Bound projects:

Flood Mitigation Phase 1

  • Rock protection and stream stabilization work
  • Multi-use trail installation 
  • Irrigation water line installation 
  • Landscaping improvements and soil encapsulated lifts

Flood Mitigation Phase 2

  • Breckenridge Industrial Court bridge approach and barrier curb work
  • Sanitary sewer piping and structure(s) installation
  • Earthwork for west detention basin
  • Sanitary sewer bypass pumping

Deer Creek Greenway Connector Part A

  • Multi-use trail construction
  • Site irrigation installation
  • Underground low-voltage installation
  • Signage layout and installation
  • Landscaping improvements
  • Decorative/chain link fencing installation
  • Dumpster enclosure gates and amphitheater handrails

Event Lawn/Comfort Station 

  • Completion of final punchlist work

Destination Playground

  • Installation of storm sewer piping
  • Earthwork

MoDOT Manchester Road Improvements

  • Demo, removals, grading, drainage and utility work
  • Flatwork installation(s)
  • Ornamental lighting installation

Site Cameras

See a live view of work on Brentwood Bound through the “Site Cameras” link at the top of the home page of www.BrentwoodBound.org.  