[ARCHIVED] Brentwood Bound Construction Update - December 22, 2022

BB Construction Update

On-site construction work details anticipated in the next two weeks on the Brentwood Bound projects:

Flood Mitigation Phase 1

  • Stream stabilization/improvement work 
  • Irrigation water line installation 
  • Soil encapsulated lifts and live staking
  • Gate installation

Flood Mitigation Phase 2

  • Breckenridge Industrial Court bridge approach and barrier curb work
  • Bridge approach paving
  • Sanitary sewer bypass pumping demobilization
  • Mass excavation and earthwork
  • Storm sewer installation

Deer Creek Greenway Connector Part A

  • Site irrigation installation
  • Underground low-voltage conduit installation
  • Signage layout and installation
  • Landscaping improvements (weather-pending)
  • Decorative/chain link fencing installation
  • Dumpster enclosure gates and amphitheater handrails

Event Lawn/Comfort Station 

  • Completion of final punchlist work

Destination Playground

  • Installation of storm sewer piping
  • Earthwork

MoDOT Manchester Road Improvements

  • Demo, removals, grading, drainage and utility work
  • Flatwork installation(s)
  • Asphalt paving of approaches
  • MSE retaining walls installation
  • Ornamental lighting installation

Site Cameras

See a live view of work on Brentwood Bound through the “Site Cameras” link at the top of the home page of www.BrentwoodBound.org.  

Facebook Twitter Email

Other News in Brentwood Bound

Brentwood Bound Brentwood Park

Coming in 2023: Brentwood Park

Posted on: January 4, 2023
Brentwood Bound Pedestrian Tunnel

Coming in 2023: Pedestrian Tunnel

Posted on: January 4, 2023
Playground Groundbreaking 11.3.22

Destination Playground Groundbreaking

Posted on: November 3, 2022