On-site construction work details anticipated in the next two weeks on the Brentwood Bound projects:
Flood Mitigation Phase 1
- Remaining stream stabilization/improvement work
- Remaining irrigation water line installation, including service tap
- Remaining soil encapsulated lifts and live staking
- Remaining fence and gate installation
- Remaining temporary seeding/site stabilization in disturbed areas
Flood Mitigation Phase 2
- Breckenridge Industrial Court bridge approach and barrier curb work
- Bridge approach paving
- Sanitary sewer bypass pumping demobilization and cleanup
- Mass excavation and earthwork
- Storm sewer installation
- Retaining wall installation south of Deer Creek
Deer Creek Greenway Connector Part A
- Wire terminations and underground low-voltage conduit installation
- Signage installation
- Landscaping improvements (weather-pending)
- Chain link fencing installation
- Dumpster enclosure gates
Event Lawn/Comfort Station
- Completion of project closeout
Destination Playground
- Installation of storm sewer piping
- Earthwork
MoDOT Manchester Road Improvements
- Demo, removals, grading, drainage and utility work
- Flatwork installation(s)
- Asphalt paving of approaches
- MSE retaining walls installation
- Ornamental lighting installation
- Banner pole installation
Site Cameras
See a live view of work on Brentwood Bound through the “Site Cameras” link at the top of the home page of www.BrentwoodBound.org.