On-site construction work details anticipated in the next two weeks on the Brentwood Bound projects:
Flood Mitigation Phase 1
- Substantial completion walkthrough
- Remaining irrigation water line service tap and meter installation
- Live staking installation
- Punchlist and closeout activities
Flood Mitigation Phase 2
- Bridge approach paving
- Grade beam and storm sewer box culvert installation
- Storm sewer piping installation
- Retaining wall installation south of Deer Creek
Deer Creek Greenway Connector Part A
- Remaining site electrical
- Landscaping improvements (weather-pending)
- Chain link fencing installation
- Dumpster enclosure gates
Event Lawn/Comfort Station
- Completion of project closeout
Destination Playground
- Earthwork
- Prep work for the Overlook foundation
MoDOT Manchester Road Improvements
- Demo, removals, grading, drainage and utility work
- Flatwork installation(s)
Site Cameras
See a live view of work on Brentwood Bound through the “Site Cameras” link at the top of the home page of www.BrentwoodBound.org.