BB Construction Update

On-site construction work details anticipated in the next two weeks on the Brentwood Bound projects:

Flood Mitigation Phase 1

  • Live staking installation
  • Weather-permitting landscaping
  • Punchlist and closeout activities

Flood Mitigation Phase 2

  • Concrete and asphalt paving
  • Bridge demolition
  • Storm sewer box culvert wingwall installation
  • Earthmoving and finish grading
  • Creek riffle/pool installation
  • Fencing installation

Deer Creek Greenway Connector Part A

  • Weather-permitting landscaping
  • Irrigation piping installation

Event Lawn/Comfort Station 

  • Completion of project closeout

Destination Playground

  • Earthwork
  • Prep work for the Overlook foundations

MoDOT Manchester Road Improvements

  • Demo, removals, grading, drainage and utility work
  • Flatwork installation(s)
  • Ornamental lighting and signal work