[ARCHIVED] Brentwood Bound Construction Update - March 9, 2023

BB Construction Update

On-site construction work details anticipated in the next two weeks on the Brentwood Bound projects:

Flood Mitigation Phase 1

  • Live staking installation
  • Weather-permitting landscaping
  • Punchlist and closeout activities

Flood Mitigation Phase 2

  • Concrete and asphalt paving
  • Concrete flatwork
  • Emergency cleanup of debris released into the creek from bridge demolition
  • Earthmoving and finish grading
  • Creek riffle/pool installation
  • Fencing installation

Deer Creek Greenway Connector Part A

  • Weather-permitting landscaping
  • Irrigation piping installation

Event Lawn/Comfort Station 

  • Completion of project closeout

Destination Playground

  • Earthwork
  • Prep work for the Overlook foundations
  • Retaining wall installation for the Family Pavilion

MoDOT Manchester Road Improvements

  • Demo, removals, grading, drainage and utility work
  • Flatwork installation(s)
  • MSE walls
  • Ornamental lighting
  • Signage and fencing installation

Site Cameras

See a live view of work on Brentwood Bound through the “Site Cameras” link at the top of the home page of www.BrentwoodBound.org.  

Facebook Twitter Email

Other News in Brentwood Bound

Brentwood Park Grand Opening

Opening June 2023: Brentwood Park

Posted on: January 4, 2023
Brentwood Bound Pedestrian Tunnel

Opening Soon: Pedestrian Tunnel

Posted on: January 4, 2023
Playground Groundbreaking 11.3.22

Destination Playground Groundbreaking

Posted on: November 3, 2022