On-site construction work details anticipated in the next two weeks on the Brentwood Bound projects:
Flood Mitigation Phase 1
- Weather-permitting landscaping
- Punchlist and closeout activities
Flood Mitigation Phase 2
- Irrigation waterline service tap and flush-mount hydrant pad installation
- Earthmoving and finish grading
- Multi-use trail installation
- Access road installation
- Weather-permitting landscaping
Deer Creek Greenway Connector Part A
- Punchlist and closeout activities
- Aquatic plantings
Event Lawn/Comfort Station
- Completion of project closeout
Destination Playground
- Earthwork and site grading activities
- Storm sewer installation
- Drilled pier foundation installation for the Overlook
MoDOT Manchester Road Improvements
- Demo and grading
- Flatwork installation(s)
- Sand and paver installation at pedestrian tunnel
- Signage and fencing installation
- Asphalt approaches and mainline paving
- Landscape plantings and sod
Site Cameras
See a live view of work on Brentwood Bound through the “Site Cameras” link at the top of the home page of www.BrentwoodBound.org.