On-site construction work details anticipated in the next two weeks on the Brentwood Bound projects:
Flood Mitigation Phase 1
- Landscaping and maintenance activities
- Remaining punchlist work and closeout
Flood Mitigation Phase 2
- Irrigation waterline service tap
- Finish grading
- Connection of multi-use path to Manchester Road
- Installation of soil amendments, seed, and erosion control fabric
- Landscaping plantings
Deer Creek Greenway Connector Part A
- Punchlist and closeout activities
- Landscape maintenance
Destination Playground
- Retaining wall installation
- Structural steel fabrication
- Heavy timber delivery and framing
MoDOT Manchester Road Improvements
- Flatwork installation(s)
- Ornamental lighting installation
- Signage and fencing installation
- Mainline paving
- Landscape plantings and sod
Site Cameras
See a live view of work on Brentwood Bound through the “Site Cameras” link at the top of the home page of www.BrentwoodBound.org.