On-site construction work details anticipated in the next two weeks on the Brentwood Bound projects:
Flood Mitigation Phase 1
- Landscaping and maintenance activities
- Remaining punchlist work and closeout
Flood Mitigation Phase 2
- Landscaping maintenance activities
- Punchlist and closeout activities
Deer Creek Greenway Connector Part A
- Landscape maintenance
- Aquatic plantings and protection
- Remaining signage installation
Destination Playground
- Retaining wall installation
- Structural steel fabrication and delivery
- Heavy timber delivery and framing
MoDOT Manchester Road Improvements
- Backfill and grading
- Flatwork installation
- Ornamental lighting installation
- Remaining fencing installation
- Striping
- Pedestrian tunnel finish work
Site Cameras
See a live view of work on Brentwood Bound.