The work on rebuilding Parkridge Avenue will continue as of November 2. The contractor’s plan is to proceed with work on the east side of the street while allowing residents to use their driveways as much as possible.
This is the tentative schedule:
11/2 Paving/Pouring
11/3 Paving/Pouring
11/4 Paving/Pouring
11/7 Paving/Pouring
11/7 Removals
11/8 Removals
11/9 Removals
11/11 Removals
Questions? Please contact Brentwood Project Manager Kyle Allen, 314.963.8668.