The work on rebuilding Parkridge Avenue continues. Within the next few days, the contractor (Byrne & Jones) plans to start at Litzsinger Road and begin pouring concrete back into the areas that are torn out. They will focus on pouring 200-250 feet at a time. This may temporarily prevent residents from accessing driveways. To alleviate this situation, the contractor will fill in the voids with more gravel for parking. The goal is to be able to have vehicles parked and driving along Parkridge in time for Thanksgiving.
Questions? Please contact Brentwood Project Manager Kyle Allen, 314.662.2794.