On-site construction work details anticipated in the next two weeks on the Brentwood Bound projects:
Flood Mitigation Phase 1
- Landscape maintenance activities
- Remaining punchlist work and closeout
Flood Mitigation Phase 2
- Installation of remaining aquatic plantings
- Landscape maintenance activities
- Remaining punchlist work and closeout
Deer Creek Greenway Connector Part A
- Landscape maintenance activities
Destination Playground
- Segmental retaining wall installation
- Installation of curbs and playground equipment foundations
- Structural steel delivery and installation for the Overlook
- Heavy timber delivery and framing